Pipe Networks Data Centre, Cromer NSW 2099
2 x 2000Amp Main Switchboards and UPS systems installation
This project had a compressed construction programme of 20 weeks, with a team of 8 x electrical tradesman and 6 x apprentices working 12hr shifts we managed this programme and completed the project 1 week ahead of the programmed completion date.